Vision:
Be One of the leading Power Producers in the Great Lakes Region
Mission:
Sustainably generate Reliable, quality and affordable Electricity for Socio- Economic Development

General Narrative

The 183MW Isimba Hydro Power Project (HPP) is located 4km downstream of Simba Falls on the River Nile, approximately 50km downstream of the Source of the Nile. The project site is about 21km from Kayunga Town as the nearest town and about 65km from Jinja Town. The Power Station will be installed with four vertical Kaplan turbine generator units with a capacity of 45.8MW per unit, thereby providing a combined installed capacity of 183.2MW.

Key Dates

  • 05th October 2013: Construction works launched by President Yoweri .K. Museveni
  • 30th April 2015 :  Project Commencement Date

 

Implementing Agency

Uganda Electricity Generation Company Limited

Contractor

China International Water & Electric Corporation

Project Duration

47 months

Project Cost

567.7 USD Million

Government of Uganda - 15%

EXIM Bank(Loan china) - 85%

Funding Agency

The People’s Republic of China

Owner's Engineer

ARTELIA EAU & ENVIRONMENT IN ASSOCIATION WITH KKATT CONSULT LIMITED

Project Management Consultant (PMC)

N/A

Capacity

183 MW

Expected Completion Date

31st March, 2019

Project Status

 

Civil Works

Concrete works approx. 99.8%, gravity dams 1 & 2 completed, spillways 1 & 2 completed, tailrace apron completed, wall cladding of powerhouse building using masonry blocks ongoing, roofing works (roof truss and roof covering) completed, By the end of August 2017, Concreting of Unit 1, 2, 3 and 4 were at elevations 1045.45, 1045.45, 1043.71 and 1043.71 respectively. RED material placement of clay, coarse filter, fine filter, and rock fill is ongoing and 95% physical progress has been attained. LED is 99.9% complete. Decoration works & tiling in the powerhouse is underway. The Amount of civil works certified as completed is 91.74% as at 30 August, 2018.

 

Electromechanical Works

EoT Crane installed and tested, upstream and downstream gantry cranes, cooling units are already delivered to the site. Approximately 99% of EM works at the spillways, 83% of EM works in the powerhouse & 78% of EM works at the switchyard was by the end of August 2018 certified as completed. Total certified works stand at 92.79%

Hydro mechanical works

Embedment works on all units and spillways completed, draft tubes, draft tube cones, lower spillway radial gates, draft tube gates, trash racks and hydraulic gates and hydraulic hoists installation completed. Approximately 95.71 % of the hydro-mechanical works have been certified as completed. Unit 1 stands at 99%, Unit 2 98%, Unit 3 70%, unit 4 90% (preparation to install guide vanes). Total certified progress stands at 97.99%

Transmission line

Design 100%, Concrete casting for tower foundations 149/149, Tower Erection 149/149, Tower Grounding 149/149 Cable & OPG Wire stringing (KM) 41.5 is done. Dry testing ongoing. 86.07% works were certified complete by end of August 2018.

Percentage of All works completed

Total overall completed work is at 95%