General Narrative
The 183MW Isimba Hydro Power Project (HPP) is located 4km downstream of Simba Falls on the River Nile, approximately 50km downstream of the Source of the Nile. The project site is about 21km from Kayunga Town as the nearest town and about 65km from Jinja Town. The Power Station will be installed with four vertical Kaplan turbine generator units with a capacity of 45.8MW per unit, thereby providing a combined installed capacity of 183.2MW.
Key Dates
- 05th October 2013: Construction works launched by President Yoweri .K. Museveni
- 30th April 2015 : Project Commencement Date
- 21st March, 2019: Project Commissioned
Implementing Agency |
Uganda Electricity Generation Company Limited |
Contractor |
China International Water & Electric Corporation |
Project Duration |
47 months |
Project Cost |
567.7 USD Million Government of Uganda - 15% EXIM Bank(Loan china) - 85% |
Funding Agency |
The People’s Republic of China |
Owner's Engineer |
ARTELIA EAU & ENVIRONMENT IN ASSOCIATION WITH KKATT CONSULT LIMITED |
Project Management Consultant (PMC) |
N/A |
Capacity |
183 MW |
Expected Completion Date |
31st March, 2019 |
Project Status |
|
Civil Works |
Concrete works approx. 99.8%, gravity dams 1 & 2 completed, spillways 1 & 2 completed, tailrace apron completed, wall cladding of powerhouse building using masonry blocks ongoing, roofing works (roof truss and roof covering) completed, By the end of August 2017, Concreting of Unit 1, 2, 3 and 4 were at elevations 1045.45, 1045.45, 1043.71 and 1043.71 respectively. RED material placement of clay, coarse filter, fine filter, and rock fill is ongoing and 95% physical progress has been attained. LED is 99.9% complete. Decoration works & tiling in the powerhouse is underway. The Amount of civil works certified as completed is 91.74% as at 30 August, 2018.
|
Electromechanical Works |
EoT Crane installed and tested, upstream and downstream gantry cranes, cooling units are already delivered to the site. Approximately 99% of EM works at the spillways, 83% of EM works in the powerhouse & 78% of EM works at the switchyard was by the end of August 2018 certified as completed. Total certified works stand at 92.79% |
Hydro mechanical works |
Embedment works on all units and spillways completed, draft tubes, draft tube cones, lower spillway radial gates, draft tube gates, trash racks and hydraulic gates and hydraulic hoists installation completed. Approximately 95.71 % of the hydro-mechanical works have been certified as completed. Unit 1 stands at 99%, Unit 2 98%, Unit 3 70%, unit 4 90% (preparation to install guide vanes). Total certified progress stands at 97.99% |
Transmission line |
Design 100%, Concrete casting for tower foundations 149/149, Tower Erection 149/149, Tower Grounding 149/149 Cable & OPG Wire stringing (KM) 41.5 is done. Dry testing ongoing. 86.07% works were certified complete by end of August 2018. |
Percentage of All works completed |
Commissioned on 21st March, 2019 |